article thumbnail

Imperial Oil ups costs of Kearl oil sands initial development 18% to $12.9B

Green Car Congress

Imperial Oil has raised the expected final cost for the Kearl oil sands initial development to $12.9 billion, up 18% from the 2011 figure of $10.9 billion barrels at a unit development cost of approximately $6.80 The Kearl expansion project, sanctioned in 2011 for $8.9 per barrel.

Oil-Sands 257
article thumbnail

Statoil postponing Corner oil sands project for minimum of 3 years; rising costs, limited pipeline access

Green Car Congress

Statoil will postpone the previously planned Corner field development at the Kai Kos Dehseh (KKD) oil sands project in Alberta, Canada, for a minimum of three years, due in part to rising labor and materials costs and market access issues including limited pipeline access. —Statoil Canada country manager Ståle Tungesvik.

Oil-Sands 225
article thumbnail

Imperial Oil sanctions Kearl Oil Sands expansion project

Green Car Congress

Imperial Oil Limited’s board of directors has approved the expansion phase of the Kearl Oil Sands Project, a surface mining operation under construction northeast of Fort McMurray, Alberta. Imperial Oil’s share of the Kearl Oil Sands asset is 71%. billion (US$10.6 per barrel. billion barrel resource.

Oil-Sands 210
article thumbnail

Fluid thermal processing of Mongolian oil sands

Green Car Congress

A study by a team from the State Key Laboratory of Heavy Oil Processing, China University of Petroleum found that fluid thermal processing of. il sands is a feasible process for the production of an upgraded bitumen-derived liquid from Inner Mongolian oil sand. Oil sands exploration in Xing’an region.

Oil-Sands 218
article thumbnail

Researchers propose framework for CCS infrastructure optimization to reduce GHG emissions from oil sands extraction and processing

Green Car Congress

The width of the pipeline network (green lines) is proportional to CO 2 flow; the largest CO 2 flow is approximately 36 MtCO 2 / yr for the $155/tCO 2 scenario (pipeline leaving the Athabasca oil sands area). Costs are in $US 2011. Credit: ACS, Middleton and Brandt. Click to enlarge. 15 years alone.

Oil-Sands 225
article thumbnail

Enbridge to build $1.3B Woodland Pipeline Extension to support Kearl oil sands project; 400kbpd initially

Green Car Congress

The project has an estimated cost of $1.3 The Woodland Pipeline Extension is being constructed to serve the Imperial Oil and ExxonMobil Kearl oil sands project and its recently announced expansion. billion to service the increasing requirements of the Alberta oil sands producers.

Oil-Sands 210
article thumbnail

MEG Energy moving ahead with 35,000 barrels per day oil sands expansion; $1.4B estimated total cost

Green Car Congress

Canada-based MEG Energy’s board of directors has approved 2011 capital investment of approximately $900 million and the final cost estimate for the 35,000 barrels per day Phase 2B oil sands expansion at the Christina Lake in-situ project. The 2011 budget includes $80 to $90 million for core drilling and seismic.

Oil-Sands 186