Altairnano to supply 10 MW Energy Storage System to INE in El Salvador

Green Car Congress

INE), one of El Salvador’s largest electric generation utilities, to provide a turnkey 10 MM ALTI-ESS advanced li-ion battery system for frequency control. The contract, valued at US$18 million, requires Altairnano to provide a complete turnkey installation at INE’s Talnique power station, including all phases of site preparation, system installation, testing and commissioning. Altair Nanotechnologies, Inc. has signed a binding contract with Inversiones Energéticas, S.A.

Altairnano selected by El Salvador utility to provide 10 MW Li-ion ALTI-ESS for frequency control

Green Car Congress

one of El Salvador’s largest electric utilities, has selected Altair Nanotechnologies, Inc. The system will be located at INE’s Talnique power station site. The ALTI-ESS system, by providing frequency control for the grid, enables INE to better utilize its electricity generation facilities, while improving the overall electric grid reliability. ( Inversiones Energéticas, S.A. de C.V.,